Tesla’s new Cloverdale station takes instructions from Pacific Gas and Electric rather than simply drawing power at a fixed rate. The site, located at Penny Faire Plaza, runs eight V4 stalls rated at up to 500 kW each, operates 24/7, and is open to both Tesla vehicles and compatible non-Tesla EVs using NACS adapters, according to TeslaNorth reporting.
How Flex Connect Actually Works
PG&E uses the IEEE 2030.5 protocol to deliver power-limit schedules to the station, with scheduling capability extending up to 72 hours ahead.
PG&E’s Flex Connect program allows the utility’s distributed-energy-resource management system to send power-limit schedules directly to participating charging sites, according to PG&E’s Flex Connect fact sheet. The Cloverdale station communicates with the grid using the IEEE 2030.5 protocol, the same standard utilities use to coordinate with solar inverters and batteries.
When local grid conditions tighten, PG&E can instruct the station to reduce its electricity draw rather than exceed available distribution capacity. A California Public Utilities Commission report notes PG&E has demonstrated scheduling capability extending up to 72 hours ahead for participating sites.
Our Cloverdale, CA Supercharger is a PG&E Flex Connect site, talking to the grid over IEEE 2030.5 to open faster.
— Tesla Charging (@TeslaCharging) November 17, 2026Why Not Just Wait for the Full Grid Upgrade?
Flex Connect lets a station open and serve drivers within the grid’s current limits while the underlying infrastructure work continues.
Grid upgrade timelines can delay site openings, according to PG&E documentation. Flex Connect functions as a bridge, letting a station open and serve drivers within the grid’s current limits while the underlying infrastructure work continues.
The program is not Tesla-exclusive. Other qualified operators that satisfy PG&E’s technical and interoperability requirements may also be able to participate.
The Tradeoff Drivers Should Understand
Utility-imposed limits can slow charging during grid stress periods, and whether drivers receive advance notice of those limits remains unconfirmed.
The 500 kW stall rating reflects maximum capability, not a guaranteed output for every session. Charging power also depends on vehicle acceptance, battery state, and stall sharing, independent of any utility limit.
During periods of grid stress, PG&E can reduce the station’s total available power, meaning individual charging sessions may run slower than the advertised maximum, per TeslaNorth. Whether Tesla’s app or the station itself will notify drivers when a reduced power limit is active has not been confirmed, according to available reporting.
Where This Fits in a Growing Network
Flex Connect could help Tesla and other operators reach smaller or capacity-constrained communities where conventional upgrades would otherwise slow deployment.
Tesla’s Supercharger network surpassed 85,000 stalls across more than 9,000 locations worldwide in 2026, according to NotATeslaApp reporting. Programs like Flex Connect could help expand that footprint into smaller communities where the local grid cannot immediately support a full fast-charging load; that conclusion follows from PG&E’s stated program purpose, not a confirmed Tesla deployment strategy.